BUDGET PROCESS OF PUERTO RICO
The drafting of the Operation Expenditures and Permanent Improvements budget begins around 15 months prior to each fiscal year when the Office of Management and Budget (OMB) prepares the general, fiscal and program norms that must guide the agencies into the drafting of their budget requests. The budget process involves several governmental agencies, as well as the participation of all the units of the Office of Management and Budget. The budget process includes the following phases and activities:
|
PHASES AND ACTIVITIES |
DURATION |
RESPONSIBLE UNIT |
|
Budget Onset |
March to January of the following year |
|
|
Planning and founding of fiscal and program norms for the budget process. |
February to March |
Director and OMB's Operation Area |
|
Analyzes programs, proposals, economic and budgetary aspects of each governmental agency. |
March to June |
OMB's Operation Area |
|
Executive meetings or administrative hearings with the agencies to discuss the budget proposal, as requested by Agency Chief |
June to October |
OMB with the agencies |
|
Executive meetings between the Budget Director and Agencies Executive Directors to discuss their proposals, as requested by Agency Chief. |
October to December |
OMB with the agencies |
|
Drafting of the General Fund and Special Funds revenue estimates, analysis of the public debt and the Government's borrowing margin. |
December to January |
OMB's Global Unity Processes Coordination, DOT, CRIM, and GDB |
|
Drafting of the budgetary recommendations report for the Governor. |
December to January |
OMB's Operation Area |
|
Administrative hearings with the Governor to discuss the budgetary proposals and recommendations . |
January |
Governor's Office, OMB, Planning Board, Governmental Agencies and Departments |
|
Draft and submit to the Planning Board a summary of the operation expenditures and permanent improvements recommended budget to make sure it is in agreement with the Four Year Investment Plan. |
December |
OMB's Global Unit Processes Coordination |
|
Drafting of the Budget Document which the Governor presents to the Legislative Assembly for its study and approval. |
December to January |
All OMB units |
|
Draft preliminary law plans over budget assignments and the revision of the fiscal and budgetary legislation to implement the budget and authorize the bond issues and all related projects. |
December to January |
OMB's Operations Area |
|
Delivery of Budget Document to the Legislative Assembly. |
February |
OMB's General Services Unit |
|
Legislative revision and Approval of the Governor's Recommended Budget |
February toMay |
|
|
Assessment of the submitted budget. |
February to May |
Senate and Congress Commissions |
|
Appearance before the Commissions to explain the budget and legislation under study. |
February to May |
Agencies and Departments, OMB's Managers and Director |
|
Budget approval by the Governor The Governor signs the General Budget's Joint Resolutions and Special Resolutions to operations expenditures and permanent improvements which will go into effect on the first of July of each fiscal year, and all other budgetary laws. |
May - June May to June |
|
|
Budget Administration |
|
|
|
July to June of each Fiscal Year |
July |
OMB's Operation Area |
|
Authorization for the accounting and the use of special assignments for operation expenditures and permanent improvements, according to the established work plans. |
July |
OMB's Operation Area |
|
Follow up and analyze agencies disbursements. |
July to June |
OMB's Operation Area |
|
Investment assignments and permanent improvements control, requiring progress reports from agencies. |
July to June |
OMB's Operation Area |